Topic: Full Load Generator Test - Wednesday April 26th (Read 575 times)
|
|
AlphaWolf
|
As a part of our quarterly facilities testing and inspection, we will be conducting a full-load generator test at our data center on Wednesday, April 26th, 2006, from 0800hrs to 1200hrs CDT.
This test is necessary in order to ensure that we are providing you with our high availability offerings, and will require a cut over of power from the utility grid to the generator for the duration of the test. We do not anticipate any downtime for our customers during this maintenance window; Thank you for your cooperation with us during this generator test, and please feel free to let us know if you have any questions.
|
|
|
|
|